PROJECTS AT A GLANCE

Icon 3
Key dates for our key rail schemes

WIRRAL LOOP LINE TRACK RENEWAL

Project commences: 3rd January 2017

Project completion:  18th June 2017

Work is planned in three phases:

  • Phase: One: 3rd Jan – 12th Feb
  • Phase Two: 13th Feb- 29th May
  • Phase Three: 30th May- 18th June

NEW & IMPROVED RAIL STATIONS

Newton le Willows station

Project commences: December 2016  

Expected project completion: March 2018 

Maghull North (new station)

Project commences: August 2017                        

Expected project completion: May 2018

LIVERPOOL LIME STREET IMPROVEMENT PROGRAMME

Project commences: Spring 2017  

Expected project completion:  2018

Work is planned in two phases:

Autumn 2017

Dates in 2018

IMPROVED SERVICES

Huyton to Roby upgrade (4th Track)

Project commences: 2014

Expected project completion: October 2017

New Liverpool to Chester Service (Halton Curve)

Project commences: Summer 2017 

Expected project completion: December 2018 

Weaver to Wavertree re-signalling

Project commences: Summer 2016 

Expected project completion: Spring 2019